Given the commercial imperative, we expedited the design development and tender process, enabling early contractor engagement and a tightly controlled lead-in period. The scope of works included significant upgrades to the building’s fabric and services, alongside extensive replacement of areas of the warehouse concrete slab to address long-term performance and durability.
The refurbishment incorporated a range of sustainability and occupier-focused improvements, including the installation of photovoltaic panels, electric vehicle charging infrastructure, a new VRF heating and cooling system and energy-efficient LED lighting throughout. These measures were key to enhancing the building’s operational efficiency and marketability within a highly competitive logistics sector.
We acted as Project Manager throughout, balancing programme acceleration with cost certainty, quality control and robust risk management to deliver a market-ready asset.

Services: Project Management, Design and Specification, Contract Administration, Cost Management and Principal Designer (CDM)
Client: Oxenwood Real Estate
Sector: Industrial Construction value: £3.2m (£10 / ft2)
Programme: 30 weeks (on-site)
Sustainability: A EPC rating
Contractor: Bowden Moss